Reference Sample
Project Period: 16 months
Shut-Down: 69 days
New Preheater & Calciner:
- New preheater complete
- New low-NOx calciner incl. comb chamber
- New tertiary air duct
- New hot gas duct
- New preheater fan
- Kiln shortening
- New kiln inlet sealing
- New kiln inlet chamber
Project Perio: 8 months
Shut-Down: 39 days
Modification of Preheater & Calciner:
- disassembly of preheater equipment except
- cyclone cone stage 2 & 4
- meal pipes satge 2 & 4
- installation of new preheater equipment
- extension exisiting 2 string calciner
- new hot gas duct