Reference Sample

Project Period: 16 months

Shut-Down: 69 days

New Preheater & Calciner:

 

  • New preheater complete
  • New low-NOx calciner incl. comb chamber
  • New tertiary air duct
  • New hot gas duct
  • New preheater fan
  • Kiln shortening
  • New kiln inlet sealing
  • New kiln inlet chamber


Project Perio: 8 months

Shut-Down:  39 days

 

Modification of Preheater & Calciner:

 

  • disassembly of preheater equipment except
    • cyclone cone stage 2 & 4
    • meal pipes satge 2 & 4
  • installation of new preheater equipment
  • extension exisiting 2 string calciner
  • new hot gas duct